A chart that shows the tasks of a project as horizontal bars along a timeline, with each bar's position and length showing when the task starts and ends.
Example
ILLUSTRATION based on Raket Parts B.V. Raket pays external consultants for an ERP project (ledger account X-GL-6940). A Gantt chart of that project could show: design, January to March; data migration, March to June; testing, May to July; go-live, August. Overlapping bars show where teams work in parallel.
Raket Parts B.V. is a fictional company created for Insyt.
For your role
Choose your role to see what this term means in your work.
Why it matters
It makes timelines, overlaps and dependencies easy to see and to discuss.
Where it is used
Project plans, delivery roadmaps and programme updates. Used by project managers, programme managers and team leads.