Velocity

  • Business, finance and operations

Definition

The amount of work a team completes in a sprint, used to plan future sprints.

Example

120 story points completed over 4 sprints gives an average velocity of 30.

For your role

Choose your role to see what this term means in your work.

Why it matters

It helps teams plan realistic sprint commitments.

Where it is used

Sprint reviews and delivery planning.

How to calculate it

Total story points completed ÷ number of sprints

Worked example

120 story points completed over 4 sprints gives an average velocity of 30.