Targets, progress and status

Burndown chart

Tracks remaining work over time against an optional ideal trajectory.

  • Chart
  • Progress
  • Trend over time

What it answers

Is remaining work declining as expected?

Shape
Remaining-work line and plan line
What it shows
Pace and remaining workload.

Example

The question

Will the team finish the sprint’s work on time?

Story points remaining in sprint 14, day by day

Story points remaining in sprint 14, day by dayRemaining work falls from 60 to 33 points by day 7, above the ideal line (18), so the team is behind pace.RemainingIdealStory points remaining0204060D0D1D2D3D4D5D6D7D8D9D10
Story points remaining in sprint 14, day by dayRemaining work falls from 60 to 33 points by day 7, above the ideal line (18), so the team is behind pace.RemainingIdealStory points remaining0204060D0D2D4D6D8D10
Remaining work falls from 60 to 33 points by day 7, above the ideal line (18), so the team is behind pace.

Illustrative data. It belongs to no company.

When to use it

Use it when

Monitoring a fixed or explicitly tracked work scope.

Avoid it when

When scope changes are hidden or effort units change.

How to read it

Read remaining work by date against a planned trajectory if present.

Note

Scope changes also affect remaining work.

The data you need

Layout
Long table
Fields
Date: date; RemainingWork: nonnegative number
One row is
One date and its remaining-work estimate. What is the grain?
Rules
Use consistent work units and scope rules. Do not cumulatively sum remaining values.
Optional
IdealRemaining or start/end dates and initial scope.
Preparation
Validate the input grain and missing values. Use consistent work units and scope rules. Do not cumulatively sum remaining values.
Units
Remaining work uses a consistent effort/item unit; do not sum snapshots across dates.
Example of the input layout: Long tableA long table: one row per observation, few columns. New data adds rows.DateRemainingWoAABBC
A long table: one row per observation, few columns. New data adds rows.

Worked example

Remaining 100,85,70 across three dates falls 15 each interval. A new scope increase would require explanation.

DateRemainingWork
2026-01-01100
2026-01-0285
2026-01-0370