PERT / project dependency network

Shows project dependencies and durations to support schedule-path analysis.

  • Diagram
  • Schedule
  • Dependency

What it answers

Which tasks constrain the project schedule?

Shape
Task nodes linked by precedence arrows
What it shows
Critical paths and slack under the model.

Example

The question

Which tasks decide when the store fit-out can finish?

Store fit-out tasks and dependencies, durations in days (PERT network)

Store fit-out tasks and dependencies, durations in days (PERT network)Tasks as boxes with durations, arrows for dependencies. The critical path in pink is design (5), permits (10), build (12), open (1): 28 days. Ordering fittings and installing IT have slack.Design5 daysPermits10 daysOrder fittings7 daysBuild12 daysInstall IT4 daysOpen1 dayPink: critical path, 28 days in total (design, permits, build, open)
Store fit-out tasks and dependencies, durations in days (PERT network)Tasks as boxes with durations, arrows for dependencies. The critical path in pink is design (5), permits (10), build (12), open (1): 28 days. Ordering fittings and installing IT have slack.Design5 daysPermits10 daysOrder fittings7 daysBuild12 daysInstall IT4 daysOpen1 day
Tasks as boxes with durations, arrows for dependencies. The critical path in pink is design (5), permits (10), build (12), open (1): 28 days. Ordering fittings and installing IT have slack.

Illustrative data. It belongs to no company.

When to use it

Use it when

Dependency-based schedule analysis with explicit assumptions.

Avoid it when

Cycles, unmodelled resource constraints or uncertain durations treated as guaranteed.

How to read it

Follow dependencies and sum durations along valid paths.

Note

Uncertain durations can use optimistic, likely and pessimistic estimates.

The data you need

Layout
Task table plus dependency table
Fields
Tasks: TaskID,Duration; Links: PredecessorID,SuccessorID
One row is
One task duration or one precedence relationship. What is the grain?
Rules
Use an acyclic dependency graph and consistent duration units. Define dependency types and lags.
Optional
Optimistic,MostLikely,Pessimistic durations for PERT estimates; standard expected duration is (O+4M+P)/6.
Preparation
Validate an acyclic dependency graph, durations and lags; calculate path totals and any PERT expected durations.
Units
Durations and lags share a unit. Path totals assume the stated dependency and resource model.
Example of the input layout: Two linked tablesTwo linked tables, joined by a shared key column.KeyValueABCKeyDetailABC
Two linked tables, joined by a shared key column.

Worked example

A3 days->B5 days->C2 days gives 10 days in sequence with no lags. Parallel branches would require comparing path totals.

Tasks: TaskIDDuration
A3
B5
C2
Links: PredecessorIDSuccessorID
AB
BC