Targets, progress and status
Product / programme roadmap
Shows intended initiatives or outcomes over strategic planning periods.
- Diagram
- Planning
- Schedule
What it answers
What initiatives are intended for each planning period?
- Shape
- Initiative blocks across time bands
- What it shows
- Sequence, overlap and planning coverage.
Example
The question
What will each team deliver over the next year?
Product roadmap, 2026 to 2027 by quarter
Illustrative data. It belongs to no company.
When to use it
Use it when
Strategic planning at appropriate precision.
Avoid it when
Treating indicative quarters as fixed delivery dates.
How to read it
Read time windows, theme and commitment labels.
Note
Distinguish commitments from indicative windows.
The data you need
- Layout
- Wide task table
- Fields
- InitiativeID: text; Initiative: text; StartPeriod,EndPeriod: date or ordered planning period
- One row is
- One initiative and its intended planning window. What is the grain?
- Rules
- Define period ordering and precision. Separate indicative windows from committed dates.
- Optional
- Theme,Owner,Status,Confidence or outcome description.
- Preparation
- Validate the input grain and missing values. Define period ordering and precision. Separate indicative windows from committed dates.
- Units
- Relationships and positions have no numeric unit by default. Label any counts, durations, probabilities or weights separately.
Worked example
Research in Q1; Portal in Q2-Q3. The roadmap indicates intended windows, not an exact committed launch date.
| InitiativeID | Initiative | StartPeriod | EndPeriod |
|---|---|---|---|
| I1 | Customer research | 2026-Q1 | 2026-Q1 |
| I2 | New portal | 2026-Q2 | 2026-Q3 |