Targets, progress and status

Target-versus-actual dot plot

Positions actuals and targets on a common scale to show gaps.

  • Plot
  • Performance against target
  • Deviation

What it answers

How large is the actual-target gap?

Shape
Actual and target dots by category
What it shows
Shortfalls and excesses.

Example

The question

Which regions hit their sales target?

Sales against target by region, 2025 (EUR million)

Sales against target by region, 2025 (EUR million)Dot is actual, white line target; cyan dots met target, pink missed. North 42 against 40; South 35 against 38; East 28 against 25; West 51 against 50; Central 19 against 24.ActualTargetNorthSouthEastWestCentral0102030405060EUR million+2-3+3+1-5
Sales against target by region, 2025 (EUR million)Dot is actual, white line target; cyan dots met target, pink missed. North 42 against 40; South 35 against 38; East 28 against 25; West 51 against 50; Central 19 against 24.ActualTargetNorthSouthEastWestCentral0102030405060EUR million+2-3+3+1-5
Dot is actual, white line target; cyan dots met target, pink missed. North 42 against 40; South 35 against 38; East 28 against 25; West 51 against 50; Central 19 against 24.

Illustrative data. It belongs to no company.

When to use it

Use it when

Precise target comparisons across metrics with compatible units.

Avoid it when

Mixed units without separate panels or an unclear target definition.

How to read it

Compare actual and target positions on the same scale.

Note

Often a paired-dot or dumbbell design.

The data you need

Layout
Wide summary table
Fields
Metric: text; Actual: number; Target: number
One row is
One metric with its actual and target values. What is the grain?
Rules
Match units and periods. Define whether higher or lower values are better.
Optional
Optional range boundaries such as PoorMax,FairMax,GoodMax.
Preparation
Confirm the metric definition, reporting period, target and favourable direction. Calculate rates or progress before applying transparent status rules.
Units
State each metric's unit. Achievement or completion needs its goal/baseline denominator; status colours and ordinal ratings are not numeric units.
Example of the input layout: Wide summary tableA wide table: one row per item, with a separate column for each measure or period.MetricV1V2V3V4V5ABC
A wide table: one row per item, with a separate column for each measure or period.

Worked example

Sales actual 80, target 100 gives a 20-unit gap. Put both dots on one axis.

MetricActualTarget
Sales80100
Renewals7275