Milestone status chart
Shows planned and actual or forecast milestone dates with completion status.
- Chart
- Schedule
- Status
What it answers
Which milestones are complete, due or delayed?
- Shape
- Dated milestone markers
- What it shows
- Slippage and upcoming commitments.
Example
The question
Which project milestones are done, late or still ahead?
ERP upgrade milestones, 2026
Illustrative data. It belongs to no company.
When to use it
Use it when
Tracking discrete project events.
Avoid it when
When durations or task dependencies are needed instead.
How to read it
Compare planned, actual and forecast date markers with status.
The data you need
- Layout
- Long table
- Fields
- Milestone: text; PlannedDate: date; Status: category
- One row is
- One milestone and its planned date/status. What is the grain?
- Rules
- Use consistent dates. Actual and forecast dates must be distinguished.
- Optional
- ActualDate,ForecastDate,Owner,Project.
- Preparation
- Validate the input grain and missing values. Use consistent dates. Actual and forecast dates must be distinguished.
- Units
- Use the measured variable's stated unit consistently. No denominator is implied unless the value is a rate or proportion.
Worked example
Design plannedJan 15, actualJan 20 is 5 calendar days late. Launch plannedMar 1 remainsPlanned without an actual date.
| Milestone | PlannedDate | Status |
|---|---|---|
| Design | 2026-01-15 | Complete |
| Launch | 2026-03-01 | Planned |