Targets, progress and status
Gantt chart
Shows task start and end dates with optional progress and dependencies.
- Chart
- Schedule
- Progress
What it answers
When are tasks scheduled and how do they overlap?
- Shape
- Horizontal duration bars on a calendar
- What it shows
- Overlap, duration and slippage.
Example
The question
Is the website project on schedule, task by task?
Website relaunch plan, weeks 1 to 12 (Gantt chart)
Illustrative data. It belongs to no company.
When to use it
Use it when
Project scheduling with actual task durations.
Avoid it when
When calendar assumptions or dependencies are omitted from a schedule claim.
How to read it
Read each task's start/end against the same calendar.
Note
Use consistent dates, duration units and working-calendar assumptions.
The data you need
- Layout
- Wide task table
- Fields
- TaskID: text; Task: text; StartDate,EndDate: dates
- One row is
- One scheduled task. What is the grain?
- Rules
- Require EndDate >= StartDate. Define inclusive/exclusive endpoints and working calendar.
- Optional
- ProgressFraction,Owner,PredecessorIDs,Milestone flag.
- Preparation
- Validate the input grain and missing values. Require EndDate >= StartDate. Define inclusive/exclusive endpoints and working calendar.
- Units
- Calendar dates andexplicit duration units; inclusive endpoints and working-day calendars change durations.
Worked example
DesignJan 1-Jan 15; BuildJan 16-Feb 15. Under inclusive dates, durations are 15 and 31 calendar days; business-day durations differ.
| TaskID | Task | StartDate | EndDate |
|---|---|---|---|
| T1 | Design | 2026-01-01 | 2026-01-15 |
| T2 | Build | 2026-01-16 | 2026-02-15 |